Wuchuan mercury mine mill operation utilization rate

Wuchuan mercury ore mill operation efficiency

project

unit

Best level of history

1984

Annual working day

day

288

276

Mill operating rate

%

86.9

83.6

Mill utilization

%

84.0

74.4

Main reasons for parking and working hours

Overhaul, power outage and no mine

Parking for 42 days

Parking for 54 days

Volume utilization factor

d/m 3 ·h

0.86

0.82